Project Schedules and Updates

W.G. Davis Building Renovation Project - Meeting Place

The renovation work in the W.G. Davis Meeting Place that began in the Summer of 2018 will continue throughout 2019 and is estimated to be completed this autumn.   

WHERE:               Davis Building, J and K Blocks

WHEN:                 Throughout 2019.  (Estimated Completion Date: Autumn 2019)

Maintenance Period: 
Monday, July 30, 2018 - Saturday, November 30, 2019

Campus Exterior Projects

Project Name Project Manager Status
P8 Snow Walls

UTM K. Ngo

On Hold
Sports Fields UTM K. Ngo On Hold

Campus Wide Projects

Project Name Project Manager Status
Utilities Infrastructure Master Plan UTM A.Azhari Planning
UTM Modular Building 2017 UTM M. Thomas Design

Alumni House

Project Name Project Manager Status
     

CCT

Project Name Project Manager Status
CC 1030S/1105S Stair Treads Replacement

UTM K. Ngo

Design
CC4128 Reno UTM M. Thomas Design

CUP

Project Name Project Manager Status
Concrete Condition Assessment UTM R.Seto Design
Low Voltage Switchgear Upgrade UTM J. Lee Design
TSSA Generator Fuel Storage Remediation UTM S. Hall Design
Update - Phase II UTM (tbd) On Hold
Roof Replacement UTM K. Ngo Design

Davis Building

Project Name Project Manager Status

A Block L2 L5 Auxillary Space Upgrade

3 Week Look Ahead Schedule

L5 Washrooms

3 Week Look Ahead Schedule

UTM M. Thomas / T. Ferguson

 

 

Construction

 

 

 

A Block L1 L3 L4 Auxillary Space Upgrade UTM M. Thomas / T. Ferguson Design

D Block Vacuum Pump Replacement

UTM R.Seto

Complete

ERS/GGR Teaching Labs Renovation, 1st Floor UTM M. Thomas Design
J/K/L Blocks Switchgear Retrofit UTM J. Lee Commissioning

Roof Replacement

UTM K. Ngo

On Hold

The Meeting Place

3 Week Look Ahead Schedule

UTM G. Karavelis

 

Construction

 

Vivarium Feasibility Study UTM S. Alsaady Design
DV0108 Golf Room Reno UTM M. Thomas Design

DV1114 Office Reno

3 Week Look Ahead Schedule

UTM M. Thomas

 

Construction

 

DV3200 Dean's Office Renovation (Phase I)

UTM D. Taylor

Complete

DV Dean's Office Reno (Phase II)

3 Week Look Ahead Schedule

UTM M. Thomas

 

Construction

 

Deerfield Hall

Project Name Project Manager Status
Door Sweep Replacements UTM S. Hall Design

Erindale Studio Theatre

Project Name Project Manager Status
Change Room Upgrade UTM D. Taylor Design

Greenhouse

Project Name Project Manager Status

Building Automation System Upgrade

 

UTM R.Seto

 

Construction

 

Grounds Building

Project Name Project Manager Status
     

Health Sciences Complex

Project Name Project Manager Status
Noise Control Installation UTM R.Seto Design
HSC 4th Floor Office Space UTM S.Bourguignon Design

HMALC

Project Name Project Manager Status
Building Addition UTM M. Thomas On Hold
HM240, Level 2 New Exit Door UTM S. Hall Design
Roof Replacement UTM K. Ngo Design

Instructional Centre

Project Name Project Manager Status
     

Innovation Complex

Project Name Project Manager Status
 

 

 

Kaneff Centre

Project Name Project Manager Status

Kaneff Roof Replacement

UTM K. Ngo

Commissioning

New Science Building

Project Name Project Manager Status

New Science Building

3 Week Look Ahead Schedule (Geotech Investigation)

UTM S. Al Saady Design

North Building

Project Name Project Manager Status

North Building Reconstruction - Phase 'B'

 

UTM G. Karavelis

 

Construction

 

Principal's Residence (Lislehurst)

Project Name Project Manager Status

 

 

 

RAWC

                  Project Name                                          Project Manager       Status    
Lobby Furniture Upgrade UTM S.Bourguignon Planning
Membership Desk Relocation UTM S.Bourguignon Planning
Women's Change Room Upgrade UTM T. Ferguson On Hold

Residence

Project Name Project Manager Status
McLuhan Court Transformer Remediation & Replacement

UTM J. Lee

Construction

Putnam Place Residence Renovation

3 Week Look Ahead Schedule

UTM M. Thomas

 

Construction

 

 Student Centre

Project Name Project Manager Status

Fire Alarm Upgrade

UTM S. Hall

Commissioning