Project Schedules and Updates

W.G. Davis Building Renovation Project - Meeting Place

The renovation work in the W.G. Davis Meeting Place that began in the Summer of 2018 will continue throughout 2019 and is estimated to be completed this autumn.   

WHERE:               Davis Building, J and K Blocks

WHEN:                 Throughout 2019.  (Estimated Completion Date: Autumn 2019)

Maintenance Period: 
Monday, July 30, 2018 - Monday, September 30, 2019

Temporary restriction of W.G. Davis Building, Main Entrance, beginning April 1

Beginning Monday, April 1, 2019, the W.G. Davis Building main entrance will temporarily be closed off for renovations as related to the Meeting Place Renovation project.

WHERE:

W. G. Davis Building Main Entrance, planter and sidewalk area in front of Davis Building, and Davis Front Field.

WHAT: 

Temporary construction hoarding will be erected around the main entrance of the Davis Building.

WHEN:

Starting Monday, April 1, 2019

Maintenance Period: 
Monday, April 1, 2019 - Monday, September 30, 2019

Campus Wide Annual Fire Alarm Testing (July & August 2019)

Annual fire alarm & sprinkler testing will be taking place across all buildings on campus during July & August.

Vipond (maintenance contractor) will be testing all fire alarm devices, some of which are located within private areas.

Specific schedules for each building have been distributed to departmental contacts.

Maintenance Period: 
Tuesday, July 2, 2019 - Friday, August 30, 2019

Annual Steam Service Interruption, July 17-19, 2019

WHERE:
WG Davis Building, RAWC, Health Sciences Building

 WHAT:  

The Steam supply service will be unavailable during the maintenance period

WHEN:

Starts: 5 PM on July 17th , 2019 ( Wednesday).

Completes: 11 PM on July 19th, 2019 ( Friday).

REASON:  

Repairs to steam pipes and maintenance of steam systems in CUP and tunnel

HOW THIS AFFECTS YOU:

Maintenance Period: 
Wednesday, July 17, 2019 - Friday, July 19, 2019

Crane Lift W.G. Davis Building Shipping and Receiving Area, July 22 until July 24, 2019

A crane lift at the Shipping and Receiving area of the Davis Building has been scheduled for Monday July 22 until Wednesday July 24 (inclusive).   

This work will begin at 7:00am and continue until about 5:00pm.  Please review the notice below.

 

 WHAT:           Crane lift gravel to the roof of W.G. Davis Building

WHERE:         Davis Shipping and Receiving

Maintenance Period: 
Monday, July 22, 2019 - Wednesday, July 24, 2019

UPDATE: Inner Circle Road and Relocation of Bus Stops near W.G. Davis Building

Please be advised that on Monday, July 22nd, 2019, the partial road closure of Inner Circle Road is expected to be finished as planned. 

WHERE:  Part of Inner Circle Road.

WHAT:    Re-opening of partial road closure due to construction.

WHEN:  Monday July 22nd, 2019

DURATION:  Permanent

REASON:  Road Paving Completed

HOW THIS AFFECTS YOU:

Maintenance Period: 
Monday, July 22, 2019

Campus Exterior Projects

Project Name Project Manager Status

MaGrath Valley Paving

 

UTM K. Ngo

 

Construction

 

P8 Snow Walls

UTM K. Ngo

On Hold
Sports Fields UTM K. Ngo On Hold

Campus Wide Projects

Project Name Project Manager Status

P5 Repaving/ P8 Partial Paving

3 Week Look Ahead Schedule

UTM K. Ngo

 

Construction

 

Utilities Infrastructure Master Plan UTM A. Azhari On Hold
UTM Modular Building 2017 UTM M. Thomas On Hold

Alumni House

Project Name Project Manager Status
     

CCT

Project Name Project Manager Status

Classroom Refresh (2 & 3)

UTM K. Au

Design

CC4128 Reno

UTM M. Thomas

Commissioning

CUP

Project Name Project Manager Status
AHU Replacement UTM A.Rodrigues Design
Concrete Condition Assessment UTM R. Seto Complete
CUP Expansion Feasibility Study (Phase 1) UTM J. Stille Planning
Deaerator Inspection & Controls Upgrade UTM K. Sharma Planning

Low Voltage Switchgear Upgrade

 

UTM J. Lee

 

Construction

 

Roof Replacement

3 Week Look Ahead Schedule

UTM K. Ngo

 

Construction

 

TSSA Generator Fuel Storage Remediation

3 Week Look Ahead Schedule

UTM S. Hall

 

Construction

 

Update - Phase II UTM (tbd) On Hold

Davis Building

Project Name Project Manager Status

A Block L2 L5 Auxillary Space Upgrade

3 Week Look Ahead Schedule

UTM M. Thomas / T. Ferguson

 

Construction

 

A Block L1 L3 L4 Auxillary Space Upgrade UTM M. Thomas / T. Ferguson Design
Elevator Modernization (#6 & #7) UTM  R. Seto Design
ERS/GGR/HCC Renovation, Phase I UTM M. Thomas Design

Roof Replacement

3 Week Look Ahead Schedule

UTM K. Ngo

 

Construction

 

The Meeting Place

3 Week Look Ahead Schedule

UTM G. Karavelis

 

Construction

 

Transitional Glazing (The Meeting Place)

3 Week Look Ahead Schedule

UTM K. Ngo

 

Construction

 

Vivarium Feasibility Study UTM S. Alsaady Design
DV0108 Golf Room Reno UTM K. Au Design
DV1003B Fire Pump Replacement UTM S. Hall Design

DV1114 Office Reno

UTM M. Thomas

Commissioning

DV Dean's Office Reno (Phase II)

UTM M. Thomas

Commissioning

Deerfield Hall

Project Name

Project Manager Status

Robotics Reno, Flr.3, Phase I

 

UTM K. Ngo

 

Construction

 

Starbucks

UTM M. Thomas

Design

Erindale Studio Theatre

Project Name Project Manager Status

Change Room Upgrade

3 Week Look Ahead Schedule

UTM K. Au

 

Construction

 

Greenhouse

Project Name Project Manager Status

Building Automation System Upgrade

UTM R. Seto

Commissioning

Grounds Building

Project Name Project Manager Status
     

Health Sciences Complex

Project Name Project Manager Status
HSC160 Renovation Phase I UTM K. Au Design
Noise Control Installation UTM R. Seto Design
     

HMALC

Project Name Project Manager Status

HM240, Level 2 New Exit Door

3 Week Look Ahead Schedule

UTM S. Hall

 

Construction

 

Roof Replacement

 

UTM K. Ngo

 

Construction

 

Starbucks Renovation

UTM M. Thomas

Complete

Washroom Renovation

       3 Week Look Ahead Schedule

UTM T. Ferguson

 

Construction

 

Instructional Centre

Project Name Project Manager Status
     

Innovation Complex

Project Name Project Manager Status
IC2200 Renovation

UTM K. Ngo

Design

Kaneff Centre

Project Name Project Manager Status

KN206/215 Suite Renovation

UTM M. Thomas

Design

New Science Building

Project Name Project Manager Status

New Science Building

UTM S. Al Saady Design

North Building

Project Name Project Manager Status

North Building Reconstruction - Phase 'B'

UTM G. Karavelis

Commissioning

Principal's Residence (Lislehurst)

Project Name Project Manager Status

 

 

 

RAWC

                  Project Name                                          Project Manager       Status    
Lobby Furniture Upgrade UTM S. Bourguignon Planning
Membership Desk Relocation UTM S. Bourguignon Design
Tim Horton Kiosk Relocation UTM M. Thomas Planning

Residence

Project Name Project Manager Status

McLuhan Court Transformer Remediation & Replacement

 

UTM J. Lee

 

Construction

 

Putnam Place Residence Renovation

 

UTM M. Thomas

 

Construction

 

Roy Ivor Hall A/C Replacement UTM A.Rodrigues Planning

 Student Centre

Project Name Project Manager Status