Project Schedules and Updates

Notice of Goods and Mail Deliveries to UTM Campus

The UTM Shipping and Receiving Loading Docks remain open and available to receive and direct goods and mail supporting our community members’ activities. 

 

The UTM campus remains open to receive shipments of mail and goods, including perishable ones.

It has come to our attention that all Vendors who are sending goods to UTM by courier services, particularly by way of UPS, must notify the delivery service that the UTM campus is open and able to receive these items.

Maintenance Period: 
Friday, March 20, 2020

UPDATE: W.G. Davis Building Elevator #6 & #7 Modernization

Elevators #6 and #7, original to the W. G. Davis Building, are undergoing modernization in the coming months.  They both serve J and K Blocks in the building, from levels 0 to the Penthouse. 

The attached drawing shows the locations of both elevators, at the second level of W.G. Davis Building.(Elevator #6 is closest to Tim Hortons; Elevator #7 is just off of the TFC).

WHAT:

Elevator modernization

Maintenance Period: 
Monday, March 30, 2020 - Friday, July 31, 2020

W.G. Davis Building Vivarium HVAC Upgrade, May-October, 2020

The Vivarium Temporary HVAC Upgrade project is initiated to address the current Vivarium HVAC risk of failures, particularly pertaining to Kathabar & BC-4 air handling units.  These units are beyond end of life and have become highly unreliable.  The mandate of this project is to provide backup HVAC to the Vivarium using Davis – Block ‘A’ air handling units (installed 3 years ago).  This upgrade will allow us to quickly switch to the A Block HVAC if any of the Vivarium air handling units fail.   This project will also implement redundancy to th

Maintenance Period: 
Friday, May 8, 2020

Campus Exterior Projects

Project Name Project Manager Status
Art Installations UTM K. Ngo Design

P8 Snow Walls Construction

3 Week Look Ahead Schedule

UTM K. Ngo

Construction
RLE [Robotics Laboratory Environment] Phase 1 UTM M. Thomas Planning
RLE Consulting UTM M. Thomas Planning
5 Minute Walk Reconstruction UTM K. Ngo Planning
Tunnel Repairs - Phase 1 UTM K. Ngo Planning

Campus Wide Projects

Project Name Project Manager Status
Integrated Waste Management Phase 1 UTM C. Dalton Planning

Alumni House

Project Name Project Manager Status
     

Communication, Culture, and Technology Building (CCT)

Project Name Project Manager Status

CCT BFP Installation

UTM R. Seto

Design

CCT 2nd & 3nd Floor Reno Phase 2

UTM K. Au

Planning

CCT 4th Floor Maintenance UTM K. Au Planning
CCT Ving Card Replacement UTM R. Eidukaitis Construction (no activity at present)
CCT Lighting Upgrade for Public Spaces UTM J. Lee Design
CCT3000 Expansion UTM K. Ngo Planning

Central Utilities Plant (CUP)

Project Name Project Manager Status

CUP AHU Replacement

3 Week Look Ahead Schedule

UTM A. Rodrigues

Construction

CUP Concrete Slab Replacement UTM R. Seto Design
CUP Expansion Feasibility Study (Phase 1) UTM J. Stille Design

CUP Low Voltage Switchgear Upgrade

UTM J. Lee

Construction

CUP TSSA Generator Fuel Storage Remediation

3 Week Look Ahead Schedule

UTM S. Hall

 

Construction (no activity at present)

 

CUP Office Renovation UTM M.Farrell Planning

William G. Davis Building

Project Name Project Manager Status

DV A Block L2 L5 Auxillary Space Upgrade

UTM  M. Thomas / A.McCall

Commissioning

DV A Block L1 L3 L4 Auxillary Space Upgrade

3 Week Look Ahead Schedule

UTM  M. Thomas / A.McCall Construction

DV A Block R.O. System Upgrade

3 Week Look Ahead Schedule

UTM A. Rodrigues

 

Construction

 

DV A/B/C Blocks Research UPS UTM J. Lee Planning

DV CABB Air Compressor Upgrade

3 Week Look Ahead Schedule

UTM A. Rodrigues Construction

DV Elevator Modernization (#6 & #7)

3 Week Look Ahead Schedule

UTM  R. Seto

Construction

DV ERS/GGR/HCC Renovation, Phase I

UTM  M. Thomas / A.McCall

Construction (No activity at present)

DV The Meeting Place

3 Week Look Ahead Schedule

UTM G. Karavelis

 

Construction

 

DV Transitional Glazing (The Meeting Place)

UTM K. Ngo

Commissioning

DV Vivarium Temporary HVAC Upgrade

3 Week Look Ahead Schedule

UTM A. Rodrigues 

 

Construction 

 

DV 3093F/3094G EDO & SVP & SC

UTM T. Ferguson

Commissioning

DV0108 Golf Room Reno

3 Week Look Ahead Schedule

UTM K. Au

 

Construction (No activity at present)

 

DV ERS/GGR/HCC Renovation, Phase 2

3 Week Look Ahead Schedule

UTM M. Thomas

 

Construction

 

DV ERS/GGR/HCC Renovation, Phase 3 UTM M. Thomas Design
DV1007 & 1012 Growth Chamber Reno

UTM K. Ngo

Design
DV1029 Microscope Room Suite Upgrade UTM M. Thomas / A.McCall Design

DV3014 Retrofit

3 Week Look Ahead Schedule

UTM  M. Thomas / A.McCall

 

Construction

 

DV Dean's Office Reno (Phase II)

UTM M. Thomas

Commissioning
DV2068 SCS Relocation UTM M. Kulykowsky Planning
DV2029 Dark Room UTM K. Ngo / M. Kulykowsky Design
DV2094A IEC Relocation UTM M. Kulykowsky Planning
DV2072 Classroom Reno UTM K. Au Planning
DV3020AB/5023A CPS Grad Office UTM M. Kulykowsky Design
DV2020/4023ABC BIO Grad Office UTM S. Bourguignon Design

DV3218/20 I&ITS Admin Office

UTM M. Kulykowsky

Commissioning

DV Summer Moves 2019 UTM M. Kulykowsky Commissioning

Deerfield Hall

Project Name

Project Manager Status

DH Psychology Front Desk

3 Week Look Ahead Schedule

UTM K. Au

 

Construction (No Activity at present)

 

DH4062/64 Indigenous Creation Studio

 

UTM Myron Kulykowsky

UTM Karyan Ngo

Commissioning

 

DH3000K Wall Re-finish UTM K. Au Design

Erindale Studio Theatre

Project Name Project Manager Status

Change Room Upgrade

 

UTM K. Au

 

Commissioning

 

Research Greenhouse

Project Name Project Manager Status

 

 

 

Grounds Building

Project Name Project Manager Status
     

Terrence Donnelly Health Sciences Complex (HSC)

Project Name Project Manager Status

HSC Noise Control Installation

UTM R. Seto

Commissioning

HSC160/253/263 AV Reno UTM K. Au Planning
HSC 424 Anth Sleep Lab TBD Planning

Hazel McCallion Academic Learning Centre (HMALC)

Project Name Project Manager Status
HMALC 388 390 390V Reno (One Button Studio) UTM K. Au Planning

Instructional Centre

Project Name Project Manager Status
     

Innovation Complex

Project Name Project Manager Status

IC2200 Renovation

UTM K. Ngo

Commissioning

Kaneff Centre

Project Name Project Manager Status

KN206/215 Suite Renovation

UTM M. Thomas

Design

New Science Building

Project Name Project Manager Status

New Science Building

Three Week Look Ahead Schedule

UTM L. Kim

 

Construction

 

Maanjiwe Nendamowinan

Project Name Project Manager Status

North Building Reconstruction - Phase 'B'

UTM G. Karavelis

Commissioning

MN Building Deficiencies

3 Week Look Ahead Schedule

UTM L. Kim Commissioning
DH/MN Accessibility Door Upgrades UTM L. Kim Planning
MN Mississaugas of the Credit First Nation Office UTM L. Kim Planning
MN Privacy Film Installation UTM L. Kim Planning
MN3230 Research Coworkers Hub UTM S. Bourguignon Construction

Principal's Residence (Lislehurst)

Project Name Project Manager Status

 

 

 

Recreation, Athletics and Wellness Centre (RAWC)

                  Project Name                                          Project Manager       Status    
RAWC Membership Control Desk Relocation UTM S. Bourguignon Design
RAWC 025V Security Upgrades UTM K. Au Design

Student Residences

Project Name Project Manager Status

Roy Ivor Hall A/C Replacement

Three Week Look Ahead Schedule

UTM A.Rodrigues

 

Construction

 

Schreiberwood Transformer Upgrade

Three Week Look Ahead Schedule

UTM J. Lee

 

Construction

 

ELC Cabinet Replacement

UTM K. Au

Commissioning

Residence Washrooms UTM L. Kim Planning

 Student Centre

Project Name Project Manager Status