Project Schedules and Updates

W.G. Davis Building Renovation Project - Meeting Place

The renovation work in the W.G. Davis Meeting Place that began in the Summer of 2018 will continue throughout 2019 and is estimated to be completed this autumn.   

WHERE:               Davis Building, J and K Blocks

WHEN:                 Throughout 2019.  (Estimated Completion Date: Autumn 2019)

Maintenance Period: 
Monday, July 30, 2018 - Monday, September 30, 2019

Temporary restriction of W.G. Davis Building, Main Entrance, beginning April 1

Beginning Monday, April 1, 2019, the W.G. Davis Building main entrance will temporarily be closed off for renovations as related to the Meeting Place Renovation project.

WHERE:

W. G. Davis Building Main Entrance, planter and sidewalk area in front of Davis Building, and Davis Front Field.

WHAT: 

Temporary construction hoarding will be erected around the main entrance of the Davis Building.

WHEN:

Starting Monday, April 1, 2019

Maintenance Period: 
Monday, April 1, 2019 - Monday, September 30, 2019

Davis Building Exterior Walkway Closure (above Loading Dock), from April 8 - July 19, 2019

As part of the Davis Building Roof Replacement Project, the contractor has set up their equipment and waste bin at the Davis loading dock area. They will be hoisting construction material to and from the roof.

For the safety of pedestrians and to keep anyone from walking underneath their equipment, the walkway just above the loading dock will be fenced off.  Signage will be in place indicating the closure.  This area will also be used for construction waste as it is brought down from the roof and into the waste bin. 

Maintenance Period: 
Monday, April 8, 2019 - Friday, July 19, 2019

Temporary relocation of Inner Circle bus stops

Beginning April 24, the MiWay and Brampton Transit bus stops currently located on Inner Circle Road will be relocated to the intersection of The Collegeway entrance and Outer Circle Road. 

The relocation of these stops is necessary because Inner Circle Road will be temporarily closed due to the Davis Building renovation project.  The construction involving Inner Circle Road is expected to be completed by July 22, 2019.

 There will be signage in place indicating the new temporary stops.

Maintenance Period: 
Wednesday, April 24, 2019 - Monday, July 22, 2019

W.G. Davis Building Exterior Partial Road Closure of Inner Circle Road, April 25-July 22, 2019

Please be advised there will be a partial road closure of Inner Circle Road starting April 25th to July 22nd.

WHERE:
Part of Inner Circle Road.

WHAT:  
Partial road closure due to construction.

WHEN:
Starting Thursday, April 25th, 2019.

DURATION:
Until Monday, July 22nd, 2019.

REASON:  
Required for the Meeting Place renovations.

Maintenance Period: 
Thursday, April 25, 2019 - Monday, July 22, 2019

W. G. Davis Building Meeting Place Seating Area temporary closure April 25-June 14, 2019

Please be advised that the Meeting Place seating area in the Davis Building will be temporarily closed off for the installation of the baffle ceiling starting April 25th to June 14th.

WHERE:
Davis Building, 2nd Floor, Meeting Place Seating Area (double-height space only).

WHAT:  
Installation of baffle ceiling.

WHEN:
Starting Thursday, April 25th, 2019.

Maintenance Period: 
Thursday, April 25, 2019 - Friday, June 14, 2019

Outer Circle Road Lane Reduction Thursday May 23, 2019, RAWC Crane Lift

A crane lift outside the RAWC has been scheduled for Thursday, May 23, 2019.   This work will begin at 7:00am and will conclude around 2:00pm.

WHAT:         Crane lift of equipment to RAWC roof

WHERE:       Outer Circle Road near RAWC entrance drop-off area.

Maintenance Period: 
Thursday, May 23, 2019

Davis Building Electrical Power Interruptions, Tuesday, May 28, 2019

Electrical Power Interruption, Tuesday, May 28, Davis Building

The following is a notice regarding the upcoming power interruptions in W. G. Davis Building, on Tuesday, May 28, 2019.  Attached is a drawing which outlines the various ‘blocks’ in W.G. Davis Building.

Maintenance Period: 
Tuesday, May 28, 2019

Service Interruption of Propane Gas Supply on Tuesday, May 28, 2019

Please be advised there will be a service interruption of the Propane Gas supply for a regulatory inspection, on Tuesday, May 28th 2019

WHERE:
WG Davis Building, CABB, Health Sciences Building and Central Utilities Plant

WHAT:  
The Propane Gas supply service will be unavailable during the inspection

WHEN:
Tuesday, May 28th, 2019.

DURATION:
7:30 AM to 4:30 PM

Maintenance Period: 
Tuesday, May 28, 2019

Campus Exterior Projects

Project Name Project Manager Status

MaGrath Valley Paving

UTM K. Ngo

Design

P8 Snow Walls

UTM K. Ngo

On Hold
Sports Fields UTM K. Ngo On Hold

Campus Wide Projects

Project Name Project Manager Status

P5 Repaving/ P8 Partial Paving

3 Week Look Ahead Schedule

UTM K. Ngo

 

Construction

 

Utilities Infrastructure Master Plan UTM A. Azhari Planning
UTM Modular Building 2017 UTM M. Thomas On Hold

Alumni House

Project Name Project Manager Status
     

CCT

Project Name Project Manager Status

Classroom Refresh (2 & 3)

3 Week Look Ahead Schedule

UTM K. Au

 

Construction

 

CC4128 Reno

UTM M. Thomas

Commissioning

CUP

Project Name Project Manager Status
Concrete Condition Assessment UTM R. Seto Design

Low Voltage Switchgear Upgrade

 

UTM J. Lee

 

Construction

 

TSSA Generator Fuel Storage Remediation UTM S. Hall Design
Update - Phase II UTM (tbd) On Hold

Roof Replacement

3 Week Look Ahead Schedule

UTM K. Ngo

 

Construction

 

CUP Expansion Feasibility Study (Phase 1) UTM (Planner TBD) Planning

Davis Building

Project Name Project Manager Status

A Block L2 L5 Auxillary Space Upgrade

3 Week Look Ahead Schedule

UTM M. Thomas / T. Ferguson

 

Construction

 

A Block L1 L3 L4 Auxillary Space Upgrade UTM M. Thomas / T. Ferguson Design
Elevator Modernization (#6 & #7) UTM  R. Seto Design
ERS/GGR Teaching Labs Renovation, 1st Floor UTM M. Thomas Design
J/K/L Blocks Switchgear Retrofit UTM J. Lee Commissioning

Roof Replacement

 

UTM K. Ngo

 

Construction

 

The Meeting Place

3 Week Look Ahead Schedule

UTM G. Karavelis

 

Construction

 

Transitional Glazing (The Meeting Place)

UTM K. Ngo

Design

Vivarium Feasibility Study UTM S. Alsaady Design
DV0108 Golf Room Reno UTM K. Au Design

DV1114 Office Reno

UTM M. Thomas

Commissioning

DV Dean's Office Reno (Phase II)

UTM M. Thomas

Commissioning
     
Project Name Project Manager Status

Robotics Reno

 

UTM K. Ngo

 

Construction

 

Starbucks

UTM M. Thomas

Design

Erindale Studio Theatre

Project Name Project Manager Status
Change Room Upgrade UTM D. Taylor Design

Greenhouse

Project Name Project Manager Status

Building Automation System Upgrade

 

UTM R. Seto

 

Construction

 

Grounds Building

Project Name Project Manager Status
     

Health Sciences Complex

Project Name Project Manager Status
Noise Control Installation UTM R. Seto Design
HSC 4th Floor Office Space UTM S. Bourguignon Complete

HMALC

Project Name Project Manager Status

HM240, Level 2 New Exit Door

3 Week Look Ahead Schedule

UTM S. Hall

 

Construction

 

Roof Replacement

3 Week Look Ahead Schedule

UTM K. Ngo

 

Construction

 

Starbucks Renovation

 

UTM M. Thomas

 

Construction

 

Washroom Renovation

 

UTM T. Ferguson

 

Construction

 

Instructional Centre

Project Name Project Manager Status
     

Innovation Complex

Project Name Project Manager Status
IC2200 Renovation

UTM K. Ngo

Planning

Kaneff Centre

Project Name Project Manager Status

KN206/215 Suite Renovation

UTM M. Thomas

Design

New Science Building

Project Name Project Manager Status

New Science Building

UTM S. Al Saady Design

North Building

Project Name Project Manager Status

North Building Reconstruction - Phase 'B'

UTM G. Karavelis

Commissioning

Principal's Residence (Lislehurst)

Project Name Project Manager Status

 

 

 

RAWC

                  Project Name                                          Project Manager       Status    
Lobby Furniture Upgrade UTM S. Bourguignon Planning
Membership Desk Relocation UTM S. Bourguignon Planning

Residence

Project Name Project Manager Status

McLuhan Court Transformer Remediation & Replacement

UTM J. Lee

Design

Putnam Place Residence Renovation

UTM M. Thomas

Commissioning

 Student Centre

Project Name Project Manager Status