Project Schedules and Updates

Campus Wide Annual Fire Alarm & Sprinkler Testing - July & August 2018

Annual fire alarm & sprinkler testing will be taking place across all buildings on campus during July & August. Vipond (maintenance contractor) will be testing all fire alarm devices, some of which are located within private areas. Specific schedules for each building have been distributed to departmental contacts.

Maintenance Period: 
Tuesday, July 3, 2018 - Thursday, August 30, 2018

Campus Window Cleaning

Beginning week of July 30th, Aquareach will be on campus for window cleaning activities.

The work is expected to take approximately 3 weeks.

Maintenance Period: 
Monday, July 30, 2018 - Friday, August 17, 2018

W.G. Davis Building Renovation Project - Meeting Place

We are excited to announce that the renovation work taking place in W.G. Davis’ Meeting Place will move into a new stage beginning Monday, July 30, 2018 and continue to Fall 2019.

WHERE:               Davis Building, J and K Blocks

WHEN:                 Beginning Monday, July 30, 2018

Maintenance Period: 
Monday, July 30, 2018 - Friday, August 30, 2019

UTM Annual Steam Shutdown

After stakeholder consultation, the date for the UTM Annual steam shutdown has been finalized.  The steam plant will be shutdown on Thursday, August 9th @ 10:00 p.m. for cool down.  We anticipate to have the steam plant back online on Tuesday, August 14th by 1:00 p.m. (It requires approximately 5-6 hours to get to full capacity).  Please advise if you have any concerns or comments.   

Buildings affected are listed below:

Maintenance Period: 
Thursday, August 9, 2018 - Tuesday, August 14, 2018

Campus Exterior Projects

Project Name Project Manager Status

P8 Lot EV Car Chargers

UTM J. Lee

Design

P9 Lot Repaving UTM K. Ngo Construction
Sports Fields UTM K. Ngo Design

Campus Wide Projects

Project Name Project Manager Status
Summer Moves UTM T. Ferguson In Progress
UTM Modular Building 2017 UTM M. Thomas Design

CCT

Project Name Project Manager Status

Fire Draft Stop Installation

UTM S. Hall

Complete

     

CUP

Project Name Project Manager Status
CUP Update - Phase II UTM (tbd) On Hold
     

Davis Building

Project Name Project Manager Status

DV A Block L2 L5 Auxillary Space Upgrade

UTM M. Thomas / T. Ferguson

Design

DV A Block L1 L3 L4 Auxillary Space Upgrade UTM M. Thomas / T. Ferguson Design

Condenser Water Loop Extension

UTM A.Rodrigues

Complete

ERS/GGR Teaching Labs Renovation, 1st Floor UTM M. Thomas Planning

J/K/L Blocks Switchgear Retrofit

3 Week Look Ahead Schedule

UTM J. Lee

 

Construction

 

The Meeting Place

3 Week Look Ahead Schedule

UTM G. Karavelis

 

Construction

 

Davis Roof Replacement UTM K. Ngo Planning

DV1024 Bio Herbarium Storage

3 Week Look Ahead Schedule

UTM S. Hall

 

Construction

 

DV1111 Server Room

UTM T. Ferguson

Commissioning

DV3041 Faculty Club Retrofit

3 Week Look Ahead Schedule

UTM D. Taylor

 

Construction

 

DV4026 Retrofit II

UTM M. Thomas

Construction

Vivarium Feasibility Study UTM S. Alsaady Design

Deerfield Hall

Project Name Project Manager Status
     

Erindale Studio Theatre

Project Name Project Manager Status
Change Room Upgrade UTM M. Fluturel Design

Grounds Building

Project Name Project Manager Status
     
     

Health Sciences Complex

Project Name Project Manager Status
HSC 4th Floor Office Space UTM T. Ferguson On Hold
L1 & L2 New MAM Lockers UTM T. Ferguson / N. Carreiro In Progress

HMALC

Project Name Project Manager Status
Building Addition UTM M. Thomas On Hold

HM Back up Power Remediation

3 Week Look Ahead Schedule

UTM J. Lee / UTM S. Hall

 

Construction

 

HM257/347 IT Closet Upgrade UTM M. Fluturel Planning

Instructional Centre

Project Name Project Manager Status
Subway Relocation UTM M. Thomas Design

Innovation Complex

Project Name Project Manager Status
 

 

 

   
 

Kaneff Centre

Project Name Project Manager Status

KN137 Classroom Renovation (IT Closets)

3 Week Look Ahead Schedule

UTM M. Thomas 

UTM T. Ferguson

Construction

 

Kaneff Roof Replacement UTM K. Ngo Planning

North Building

Project Name Project Manager Status

North Building Reconstruction - Phase 'B'

3 Week Look Ahead Schedule

UTM G. Karavelis

 

Construction

 

Principal's Residence (Lislehurst)

Project Name Project Manager Status

Principal's Residence Roof Replacement

3 Week Look Ahead Schedule

UTM K. Ngo

 

Construction

 

RAWC

                  Project Name                                          Project Manager       Status    
Booster Juice UTM M. Thomas Design
Pool Columns Repair UTM K. Ngo Design
Women's Change Room Upgrade UTM T. Ferguson On Hold

Residence

Project Name Project Manager Status

Erindale Hall Change Use

3 Week Look Ahead Schedule

UTM M. Fluturel

 

Construction

 

Putnam Place Residence Renovation UTM M. Thomas Design

Residence Washroom Renos 2018

3 Week Look Ahead Schedule

UTM M. Fluturel

 

Construction

 

 Science Building

Project Name Project Manager Status
Science Building UTM S. Al Saady Design

Student Centre

Project Name Project Manager Status