Project Schedules and Updates

North Bldg. Phase B - Outer Circle Roadwork April 24-May 25, 2018

North Building Phase B’s contractor Stuart Olson will be performing road work along Outer Circle Road and the laneway which connects to Parking Lot 1, April 24th to approximately May 25th, 2018.  The existing entry to Parking lot 1 will be closed for the duration of the work; the exit route will remain open and used to enter and exit Parking Lot 1.  There will be signs posted indicating the closure and a flagperson stationed at this laneway to direct vehicles to the new temporary entrance near IB Building.

Maintenance Period: 
Wednesday, April 25, 2018 - Friday, May 25, 2018

CCT Garage Camera Work

Ozz Electric will be installing conduits and cameras in all levels of the CCT garage starting May 7th and continuing until June 1, 2018. Cameras will be installed in the parking levels as wells as the stairway/elevator vestibules. Various parking spaces will be blocked off due to the work above.

 CCT garage and stairways/elevators will remain accessible. Entry and exit to the garage will remain unchanged and unaffected. Existing security monitoring in the garage will also remain unaffected.

Maintenance Period: 
Monday, May 7, 2018 - Thursday, June 7, 2018

Pedestrian Walkway Re-sloping Work

The pedestrian walkway from parking lot P9 to the link between HMALC and CCT (above CCT parking garage entrance) will be restricted from all access between May 28-June 1, 2018 for maintenance work.  (Please refer to the drawing below for location)

Armor Rock will be re-sloping the walkway and applying a new coating system.

Maintenance Period: 
Monday, May 28, 2018 - Friday, June 1, 2018

Campus Exterior Projects

Project Name Project Manager Status

Sports Fields

 

UTM K. Ngo

UTM B. Lawrence

Design

 

Campus Wide Projects

Project Name Project Manager Status
UTM Modular Building 2017 UTM M. Thomas Design
Building Condition Assessment Survey UTM K. Ngo Ongoing

CCT

Project Name Project Manager Status

Fire Draft Stop Installation

3 Week Look Ahead Schedule

UTM S. Hall

 

Construction

 

Pedestrian Walk Repair 2018 UTM K. Ngo Design

CUP

Project Name Project Manager Status

Steam Boiler Replacement - Phase II

UTM A.Rodrigues

Complete

CUP Update - Phase II UTM (tbd) On Hold

Davis Building

Project Name Project Manager Status

A&B/C Block Corridor and Elevator Lobby Upgrades

 

UTM M. Thomas

UTM T. Ferguson

Design

 

Condenser Water Loop Extension

UTM A.Rodrigues

Complete

ERS/GGR Teaching Labs Renovation, 1st Floor UTM M. Thomas Planning
J/K/L Blocks Switchgear Retrofit UTM J. Lee Design

The Meeting Place

3 Week Look Ahead Schedule

UTM G. Karavelis

 

Construction

 

Davis/Kaneff Roof Replacement UTM K. Ngo Planning
DV1024 Bio Herbarium Storage UTM S. Hall Design

DV1111 Server Room

UTM T. Ferguson

Commissioning

DV3014/3015 MMB Biology Lab Renovation

UTM M. Thomas

Commissioning

DV3041 Faculty Club Retrofit

UTM D. Taylor

Commissioning

DV4026 Retrofit UTM M. Thomas Design

Deerfield Hall

Project Name Project Manager Status
     

Erindale Studio Theatre

Project Name Project Manager Status
Change Room Upgrade UTM M. Fluturel Design

Grounds Building

Project Name Project Manager Status
Gas Pump Electrical Connection UTM K. Ngo Design
Roll Up Door Replacements UTM M. Fluturel Design

Health Sciences Complex

Project Name Project Manager Status
HSC 4th Floor Office Space UTM T. Ferguson On Hold
L1 & L2 New MAM Lockers UTM T. Ferguson Design

HMALC

Project Name Project Manager Status
Building Addition UTM M. Thomas On Hold

HM Back up Power Remediation

UTM J. Lee / UTM S. Hall

Design

HM257/347 IT Closet Upgrade UTM (tbd) On hold

Instructional Centre

Project Name Project Manager Status
Subway Relocation UTM M. Thomas Planning

Innovation Complex

Project Name Project Manager Status
 

 

 

Kaneff Centre

Project Name Project Manager Status

KN137 Classroom Renovation

UTM M. Thomas

Commissioning

North Building

Project Name Project Manager Status

North Building Reconstruction - Phase 'B'

3 Week Look Ahead Schedule

UTM G. Karavelis

 

Construction

 

Principal's Residence (Lislehurst)

Project Name Project Manager Status
Principal's Residence Roof Replacement UTM K. Ngo Planning

RAWC

Project Name Project Manager Status
Women's Change Room Upgrade UTM T. Ferguson Design

Residence

Project Name Project Manager Status
Erindale Hall Change Use UTM M. Fluturel Design
Putnam Place Residence Renovation UTM M. Thomas Design
Residence Washroom Renos 2018 UTM M. Fluturel Design

 Science Building

Project Name Project Manager Status
Science Building UTM S. Al Saady Design

Student Centre

Project Name Project Manager Status
XR250 Expert Reno UTM M. Fluturel

Planning